Breach of written contract in New Jersey
Last checked Aug 15, 2026 · LawyerUnc editorial. Educational only, not legal advice.
Elements
1
Valid contract
Offer, acceptance, consideration, and sufficiently definite terms. In writing, as required.
2
Performance or excuse
The plaintiff performed, tendered performance, or was excused.
3
Breach
The defendant failed to do what the contract required.
4
Damages
The breach caused a measurable loss. Expectation damages are the usual measure.
Burden of proof
Preponderance of the evidence.
A New Jersey fact pattern
A written home-remodel contract in Montclair with a completion date and a punch-list holdback. The contractor walks to a bigger job. Expectation damages are the cost to finish minus the unpaid contract balance, plus any enforceable delay term, if the owner was not the one holding permits.
Statute of limitations
6 years
N.J.S.A. 2A:14-1
From breach.
Open the tracker